CASES STUDIES

Generator swaps for IHS

ISH is a leading mobile communications infrastructure company in Africa . During their various roll out and capacity upgrade campaigns in Cameroon, they needed a reliable and efficient partner to perform generators swap…

Challenges:

“Perform within tight schedules of roll out campaigns, generator swaps at greenfield sites located in remote and difficultly accessible regions of Cameroon”

Solutions:

During each campaign, we have to put in place all logistics & transport operations needed to move new

generators from IHS warehouses in Douala to the various greenfield sites; as well mobilizing the necessary equipment, engineers and technicians to perform the task.

Challenges:

The small beams holding the poles were not firm enough, so they had to be replaced without affecting traffic.

Solutions:

A new support to the poles were fabricated with metal and concrete slap to replace the small beams.

Reinforcement of MTN Networks Poles

The small beams holding the poles were not firm enough, so they had to be replaced with concrete slaps…

Renovating Carventon Helicopter's Building

ISH is a leading mobile communications infrastructure company in Africa . During their various roll out and capacity upgrade campaigns in Cameroon, they needed a reliable and efficient partner to perform generators swap…

Challenges:

The paint on the building was old and pealing off and the paint on aircraft lines was fading out.

Solutions:

Retreated and painted the whole building as well as the aircraft lines.

Repairing Douala Airport Lighting Towers

TA engineering Sarl brought down its expertise and repaired the

mechanism. The lighting system was able to move up and down.TA Engineering Sarl fabricated parts which were used on the lighting towers. The project lasted for 5 days..

Challenges:

The system was unable to move up and down for about 22 years. Each time the bulbs are to be replaced, a crane had to be rented which as costly.

Solutions:

TA engineering Sarl brought down its expertise and repaired the mechanism. The lighting system was able to move up and down.TA Engineering Sarl fabricated parts which were used on the lighting

towers. The project lasted for 5 days.

Turnkey Site Construction Case study : ASTER

Aster Global Services Cameroon Limited is a subsidiary of Aster Private Ltd, providing Turnkey Solutions for the Telecommunication market in Cameroon…

Challenges:

Working within changing schedules and challenging conditions to deliver turnkey sites with special

“co-location” configuration.

Solutions:

We conduct a site survey to gather all technical & environmental data of the area that will host the new turnkey.